After months of quiet prep work, the Sacramento Kings downtown arena construction project goes public this week.
Crews will be restriping J, L and Fifth streets, pushing traffic away from the site to give the project elbow room. Workers will erect 9-foot noise-dampening walls at key spots in the streets around the project in the next few days, allowing space for the first of up to 16,500 dump truck trips hauling demolition debris and dirt over the next few months. Tractors were being delivered to the site. Some demolition begins Friday.
-- Sacramento Bee
Crews will be restriping J, L and Fifth streets, pushing traffic away from the site to give the project elbow room. Workers will erect 9-foot noise-dampening walls at key spots in the streets around the project in the next few days, allowing space for the first of up to 16,500 dump truck trips hauling demolition debris and dirt over the next few months. Tractors were being delivered to the site. Some demolition begins Friday.